Overview

New feature in version 2.6.14 introduces a way to bulk change dependency objects to Customer level whilst object type still remains allocated to site.

BASL Types

To facilitate this we have introduced a new mapping table called BASL (Before Any Sites Loaded) Types, where we add dependency objects that are moved to customer (BASL) level during a phased migration.

The BASL Types reside under Mappings->Mapping Tables

image-20250219-001328.png

By default, BASL Types contains a number of Object Types as per screen shot below. These may be added to or removed as required.

image-20250219-001615.png

Using BASL Type during migration

During a phased migration, after as per normal creating Sites from Site Suggestions, solving validation issues, performing target mapping , then selecting site to migrate, then revalidate or reallocate as requested by wrangler_

image-20250219-003015.png

On completion of validation, there will be validation rule triggered advising of detected objects that should be moved to Customer and before any sites loaded. These objects may be viewed by selecting Review Objects and if satisfied that all looks correct, select Update Objects bulk change button which will move all these objects to BASL

image-20250219-003212.png

Review Objects to move to BASL

image-20250219-003326.png

If OK with Review - select Update Objects

image-20250219-003501.png

Post bulk change, you can check individual objects where you will notice a new field, Prepare & Load With and in Override Value column you can see that Change At has moved to BASL and Prepare & Load With now states CUSTOMER

image-20250219-004443.png

Continue to solve all validation rules as required and revalidation, ON cwe move to prepare step

image-20250219-005548.pngimage-20250219-005614.png

Resolve any remaining Dependency issues

image-20250219-005807.pngimage-20250219-010457.png

Resolve these issues and restart execution, moving on to pre load stage.

image-20250219-011031.png

We need to perform another validation. Notice that we will again require an update of objects Bulk Change for dependency objects. in addition to other validation rules. Without solving any other validation issues, select Update Objects

image-20250219-011509.pngimage-20250219-011553.png

Now Re-Validate Migration again

image-20250219-011718.png

On completion of the validation, a number of sequential issues would have disappeared, now resolve any remaining pre load issues as per normal, Re-Validate Migration migration and proceed to load

image-20250219-011907.png
  • No labels